I guess it has been over a month and a half since I posted last. Really falling off this blog thing. Didn't think there was much to report as into trim and going slow but I guess there are a few things. In our defense we took a couple of weeks (more like 10 days) off to visit Kathie and John in Curacao so it is
Key Features: 16in ~R50 truss walls; ~R100 roof; insulated slab on grade (R24 below R48 in front)in floor hydronic heat; small basement for mechanical and root cellar; attached passive solar greenhouse with 3ft thick rammed earth wall; Masonry heater; solar hot water; 10KW Bergy wind turbine (grid connected) hope will also run elec. vehicle; HRV; Composting toilet; High ER fiber glass windows; Permaculture to follow. See May 16 for history, explanation of design principles and plan pictures.
Saturday, 25 February 2012
Monday, 2 January 2012
Forging ahead
Thursday, 15 December 2011
Wind turbine goes up (yesterday)
Drywall mudding is complete down stairs (except for a few spots around the stairs that got dry walled after stairs went in). Stairs (no railing yet) went in last Friday (forgot to post and take pictures).
Will add some pics (hopefully tonight). Kitchen cabinets may go in today (nope, not until next week).
A bunch of catch up photos (pretty random order as is a pain to move them around):
Will add some pics (hopefully tonight). Kitchen cabinets may go in today (nope, not until next week).
A bunch of catch up photos (pretty random order as is a pain to move them around):
Thursday, 24 November 2011
Finally an update
Some of the not so good news....
I am stiiiiiiilllll waiting for the two south doors (it is over 3 months now since we gave them our deposit), the garden (French) and the balcony door, therefore the shingling is in fact not really completed as I will have to complete around the doors after they are installed.
The driveway is not completed. I have been bugging the earth mover all summer to get it done. He came last week and did a day and a half's work and then it poured creating a giant mud bog and then he went to Florida for Holidays. I wish he had just told me he was not going to be able to get to it until late but spilt milk now.
I am stiiiiiiilllll waiting for the two south doors (it is over 3 months now since we gave them our deposit), the garden (French) and the balcony door, therefore the shingling is in fact not really completed as I will have to complete around the doors after they are installed.
The driveway is not completed. I have been bugging the earth mover all summer to get it done. He came last week and did a day and a half's work and then it poured creating a giant mud bog and then he went to Florida for Holidays. I wish he had just told me he was not going to be able to get to it until late but spilt milk now.
Saturday, 22 October 2011
Still siding, Plumbing, Electrical and Ducting roughed in
As the title says the siding is still ongoing. Takes a long time to put on cedar shingles. Have to go through the house and patch all the holes from the completed rough in of plumbing, electrical and ducting and any other areas (e.g., breaks in sole plates) before the insulation can start.
Still missing the front door, garden door and balcony door. They are supposed to be all here next week so it will then (finally) be weather and lock tight (fingers crossed).
Still missing the front door, garden door and balcony door. They are supposed to be all here next week so it will then (finally) be weather and lock tight (fingers crossed).