It has been a few days since our last post but things have been progressing (I just have not been
Key Features: 16in ~R50 truss walls; ~R100 roof; insulated slab on grade (R24 below R48 in front)in floor hydronic heat; small basement for mechanical and root cellar; attached passive solar greenhouse with 3ft thick rammed earth wall; Masonry heater; solar hot water; 10KW Bergy wind turbine (grid connected) hope will also run elec. vehicle; HRV; Composting toilet; High ER fiber glass windows; Permaculture to follow. See May 16 for history, explanation of design principles and plan pictures.
Tuesday 28 June 2011
Tuesday 21 June 2011
Thursday 16 June 2011
Tuesday 14 June 2011
Monday 13 June 2011
Maritime weather - Rained out
Added optimization for smart phones so the the site should look better on your smart phone now. FYI I
Saturday 11 June 2011
Sunday 5 June 2011
Sub Slab HDPE dimpled membrane completed
Rocks from class A gravel are making dents but do not appear to be piercing membrane. Taped all seams and around sub slab plumbing with Delta multiband tape (~$40.00 / roll 25m long by 60mm wide so pretty expensive). Vacuumed all water off (had to buy a shop vac. but should come in handy. It has a 2nd pump to pump out the water at the same time you suck it up through a garden hose) to finish but is
Friday 3 June 2011
Thursday 2 June 2011
Final Grade for pad with a bit of gravel, Delta MS HDPE membrane and slab forms
Put on a little gravel (class A, which is supposed to be ~3/4" stone minus with a lot of fines for compacting) to get to final grade. In hindsight I wouldn't have done this and just had Jeremy spend a couple more hours with the dozer and get to near final grade with the shale. We compacted the gravel with a rented plate tamper but it didn't really compress very well on the very hard packed shale. Also a